Your Maximo migration will fail without clean data. Here's exactly what to fix - asset hierarchies, duplicates, field gaps - before you move to MAS 9.
If you're a Maximo admin or maintenance engineer, you've probably had "MAS migration" on your radar for a while now. Maybe your manager has been talking about it. Maybe IBM has been calling. Maybe you've been quietly ignoring the whole thing, hoping it goes away.
It's not going away.
Maximo 7.6.1 base support ended on 30 September 2025. Check IBM's current terms for any extended support. Current MAS 9 releases are the target, and IBM is making it very clear: this is where Maximo is going.
Most of the migration guides out there focus on OpenShift, Kubernetes, licensing models, and infrastructure. That's all important. But here's the thing nobody wants to talk about: the data is what kills migrations. Not the infrastructure. Not the licensing. The 15 years of messy, inconsistent, "we'll-fix-that-later" data sitting in your Maximo database right now.
This article is about what to actually fix in your data before you touch MAS 9.
Planning the move? Download the free Maximo to MAS 9 Migration Checklist.
One distinction runs through everything below. A database upgrade carries your existing records across, defects included. An extract-and-reload moves the data through load tools, which can reject records that break the target rules. Bad data causes different problems on each route, so the two are called out separately where it matters.
Why MAS 9 Is Less Forgiving Than Maximo 7.6
Your old Maximo instance was tolerant of messy data because humans were the primary interface. A technician could look at a misspelled asset description and figure out what it meant. A planner could eyeball a hierarchy and mentally fill in the gaps.
MAS 9 doesn't work like that.
The architecture has changed fundamentally. MAS runs containerised on Kubernetes, not on standalone servers. MongoDB stores MAS user, application and entitlement metadata, while Manage uses Db2, Oracle or SQL Server. The whole system is built around modular services - Manage, Monitor, Health, Predict, Assist - each consuming your data through APIs that expect clean, consistent, well-structured inputs.
Here's why that matters: APIs are brittle when faced with inconsistent values or broken relationships. A human can look at "PUMP-001" and "PMP-001" and know they're the same thing. An API can't. A human can see that an asset's parent location was deleted and figure out where it should go. A load or integration through an API rejects the record.
If you're moving to MAS specifically to use the AI and IoT capabilities - Health scoring, Predict failure forecasting, Monitor sensor integration - those modules amplify data quality problems rather than solving them. Feed Predict a dataset full of duplicate assets and missing manufacturer data, and you'll get predictions that are worse than useless. You'll get predictions that make people distrust the system.
The custom workflows your team built over the past decade also need attention. Automation scripts may reference hard-coded values that exist in your legacy data but won't survive a cleanup. Escalation rules may depend on classification structures that you're about to restructure. Configuration and data are intertwined - you can't clean one without reviewing the other.
Bottom line: an upgrade brings across what Maximo 7.6 tolerated. A reload can reject it, and the applications that use the data afterwards will expose it.
The 6 Data Problems That Will Wreck Your Migration
After working with organisations going through CMMS migrations, we see the same problems over and over. Here are the six that cause the most damage - and what to do about each one.
1. Broken Asset Hierarchies
The problem: Parent-child relationships that reference deleted locations or assets. Hierarchy depth that varies wildly - some sites use 3 levels, others use 7 for equivalent structures. Locations and assets mixed inappropriately (assets sitting under assets when they should be under locations, or vice versa).
Why it happens: Over 10-15 years, different people manage the data with different standards. Sites get decommissioned but their child records aren't cleaned up. Restructures happen in the physical plant but nobody updates Maximo.
What breaks in MAS: The Spatial, Monitor, and Health modules all rely on clean hierarchies. On a reload route, broken parent references cause cascade failures - you can't import 5,000 child assets if their parent locations are invalid. On a database upgrade they come across unchanged, and the hierarchy-dependent features in MAS won't function correctly until they are fixed.
How to fix it:
- Export your full hierarchy and validate that every parent reference actually exists
- Standardise hierarchy depth across all sites - agree on a structure (typically: Site → Facility → System → Equipment → Component) and apply it consistently
- Identify and resolve all orphaned records - assets whose parent was deleted but still reference the old parent ID
- Decide whether each record should be a location or an asset - this distinction matters much more in MAS than it did in 7.6
2. Duplicate Records
The problem: The same physical pump entered three times with slight naming variations: "PUMP-CW-001", "CW-PUMP-001", and "Cooling Water Pump 1". Duplicate locations for the same physical space. Duplicate spare parts with different commodity codes pointing to the same item on the shelf.
Why it happens: Multiple people entering data over many years. Mergers and acquisitions bringing duplicate data sets. MXLoader imports using AddChange that created records instead of updating existing ones. Nobody had time to deduplicate because the system still "worked."
What breaks in MAS: Duplicates create conflicting IoT sensor mappings - which "PUMP-CW-001" does the vibration sensor belong to? Work order history gets split across duplicate records, making failure analysis unreliable. Predict and Health give inaccurate scores because they're looking at partial histories. Your spare parts inventory looks wrong because BOMs reference different versions of the same asset.
How to fix it:
- Export assets, locations, and items. Cross-reference by a combination of serial number, location, classification, and description to identify probable duplicates
- For each set of duplicates, define a "golden record" - the one that keeps all the history and becomes the single source of truth
- Merge work order history and meter readings onto the golden record before retiring the duplicates
- This is tedious work in Excel. It's exactly the kind of problem that data staging tools are designed to solve at scale
3. Empty Critical Fields
The problem: Asset criticality: blank on 60% of records. Manufacturer: blank on 40%. Model number: populated but inconsistent ("Grundfos" vs "GRUNDFOS" vs "grundfos pumps"). Serial number: blank on half your assets. Installation date: missing on anything installed before 2015 because "we didn't track that back then."
Why it happens: When Maximo was first set up, nobody enforced mandatory fields. Data was entered to get work orders raised, not to build a complete asset register. Over time, the gaps compounded.
What breaks in MAS: Missing manufacturer, model and serial data limits what Maximo Health and Predict can tell you, because it is harder to group like equipment and compare its history. Criticality analysis is meaningless if 60% of your assets don't have a criticality rating. Monitor can't alert on the right assets if it can't distinguish critical from non-critical.
How to fix it:
- Don't try to fill every field on every record - you'll never finish. Instead, identify which fields your target MAS modules actually consume and prioritise those
- For Health and Predict, useful fields include: manufacturer, model, serial number, installation date, criticality
- For Monitor: classification, location (for spatial placement), operational status
- For Manage (core): all parent references, status, description, classification
- Use a phased approach - clean the highest-criticality assets first, then work outward
4. Classification Chaos
The problem: Multiple classification hierarchies used across sites or time periods. Site A uses a custom classification tree built in 2009. Site B adopted ISO 14224 in 2018. Site C uses something that started as ISO 14224 but was modified until it no longer conforms to the standard. Classifications that were changed mid-life, breaking parent-child relationships in the classification hierarchy.
Why it happens: Standards evolve, teams change, and nobody enforces consistency across sites. Sometimes a well-meaning engineer restructures the classification tree without understanding the downstream impact on every asset that references it.
What breaks in MAS: Classification hierarchies whose parents were changed in a way that breaks the original structure carry real risk. On a reload, records can be rejected or land against the wrong class. On an upgrade, the inconsistency comes across unchanged. MAS Manage's new automation features depend on consistent classification for grouping, reporting, and PM scheduling. If your classifications are inconsistent, every report and dashboard built on them will be unreliable.
How to fix it:
- Choose one classification standard and commit to it. ISO 14224 works well for oil & gas and process industries. RDS-PP or RDS-PS suits power generation and electrical systems. SFI suits maritime. Custom systems work if they're well-documented and consistently applied
- Map every existing classification to the target standard - this is a manual exercise that requires engineering knowledge, not just data skills
- Rebuild the classification hierarchy from scratch in your target structure, then reclassify assets against it
- Do this in a staging environment, not in your live Maximo instance
5. Sequence and Key Conflicts
The problem: The next value a sequence will issue falls behind the highest ID already used in the table. This happens when data was loaded through direct SQL inserts or other routes that bypassed sequence management.
Where sequences live depends on your database:
- Maximo 7.6 on SQL Server: values are held in the MAXSEQUENCE table
- Oracle and Db2: sequences are database objects
- Manage on SQL Server: native SQL Server sequences were delivered in Manage 8, so MAXSEQUENCE is not the place to look after that change
Why it happens: Years of direct database interventions, emergency fixes, data loads from external sources, and environment refreshes that didn't properly reset sequences.
What breaks: Duplicate key errors when new records are created, whether in a reload batch or in normal use after an upgrade. On SQL Server this is error 2601. Oracle and Db2 report duplicate keys with their own error codes. On a reload, a batch can hit one conflict, be fixed and restarted, then hit another, which is how a planned weekend overruns.
How to fix it:
- Compare the highest ID in each table with the next value its sequence will issue, using the method for your database
- On Maximo 7.6 with SQL Server, correct the affected MAXSEQUENCE values
- On Oracle and Db2, reset the affected database sequences
- On Manage with SQL Server, work with the native sequences
- Document every table where you find discrepancies, as these are the tables where someone has been doing direct SQL operations
- After cleanup, enforce a policy: no direct SQL inserts into Maximo tables without managing sequences
6. Orphaned Transactional Data
The problem: Work orders referencing assets that no longer exist. PM schedules pointing to deleted routes or job plans. Meter readings for decommissioned equipment. Purchase orders linked to vendors that were removed from the vendor register.
Why it happens: When assets are decommissioned, the asset record gets set to DECOMMISSIONED status, but the related work orders, PMs, and meter readings stay behind. When someone does a bulk delete of "old" locations, the work orders that referenced those locations become orphans.
What breaks in MAS: On a reload route, the load rejects a work order whose referenced asset doesn't exist, and thousands of orphaned records mean thousands of rejected rows. On a database upgrade the orphans come across unchanged, and surface later in reports, integrations and the applications that use the data.
How to fix it:
- Before migration, decide what transactional history you actually need to bring across. Usually the answer is: open work orders, active PMs, and the last 12-24 months of completed work orders (for Health/Predict to analyse)
- Archive everything else. IBM provides tools for archiving Maximo transaction data - use them
- For the records you are migrating, validate every foreign key reference: does the asset exist? Does the location exist? Does the job plan exist?
- Fix or remove records with broken references before a reload, or before relying on them after an upgrade
The Migration Data Sequence
Even with clean data, order matters. You can't import an asset that references a location that doesn't exist yet. You can't import a PM that references a job plan that hasn't been created.
On a reload route, load in this order. A database upgrade doesn't follow this sequence, but any corrective loads you run afterwards should.
- Organisations and sites - everything references these, so they go first
- Supporting reference data - companies, classifications, failure classes and meter definitions
- Locations - top of hierarchy down, parents before children
- Item master, including rotating items - rotating assets reference these
- Assets - each asset maps to a location and references a classification
- Spare parts - link items to assets, so both must exist first
- Job plans and safety plans - define the work that PMs will schedule
- Routes and PMs - reference assets, locations and job plans
- Open work orders - reference everything above
- Meter readings - reference assets and their meters
Each layer depends on the one before it. If locations have errors, every asset mapping fails. If classifications are wrong, every attribute assignment fails. This is why the data quality work happens before the technical migration, not during it.
Maximo 7.6 to MAS Migration: What to Assess, Clean, Validate and Reconcile
Upgrades and consolidations or reimplementations move data differently, as described above. The four stages below apply to both. Only the point at which you fix the data changes.
Assess
Profile each object before you plan any fixes:
- Volumes by object and site: locations, assets, classifications, items, job plans, PMs, routes, meters, open work orders and history
- Quality counts: blanks in key fields, probable duplicates, and parent or foreign key references that do not resolve
- Configuration that depends on data: automation scripts, escalations and custom fields that reference specific values
- Module needs: which fields Manage and any other MAS applications you plan to use actually consume
- Scope: what history comes across and what gets archived
Clean
Work through the six problems above in dependency order: classifications and hierarchies first, then duplicates, then field gaps, then transactional records that point at anything you changed. Record every merge and code change in a crosswalk from old value to new value, so scripts, reports and integrations can be updated to match.
Validate
Check the cleaned data against the target rules before it reaches production:
- Every parent, location, classification, item and job plan reference resolves
- Required fields are populated and values match the target domains
- Classification attributes are complete for the classes in use
- Duplicate checks return only the exceptions you have accepted
- A trial load or upgrade in a MAS test environment completes, and every rejected record is explained
Reconcile
After the trial and again after go-live, compare source and target:
| Check |
What should match |
| Record counts |
Source count, less agreed exclusions, by object and site |
| Hierarchy |
Parent and child counts, plus a sample walked by a planner |
| Open work |
Open work order count and status |
| Preventive maintenance |
Active PMs and next due dates |
| Meters |
Latest reading per meter |
| Spares |
Spare parts lists on a sample of critical assets |
Agree the tolerances and the people who sign off before the trial, not after it. Any difference that cannot be explained stops the cutover.
A Practical Cleanup Process
Here's the process that works. It's not glamorous, but it's effective.
Step 1: Audit. Export your data and profile it. Count the nulls, the duplicates, the orphaned references. Understand the scale of the problem before you touch anything. You need to know whether you're dealing with 500 issues or 50,000.
Step 2: Define standards. Agree on naming conventions, classification system, required fields, and hierarchy depth. Document these standards. Get sign-off from operations, not just IT - the maintenance team needs to own the data standards because they're the ones who'll maintain them after migration.
Step 3: Pilot. Pick one site or one asset category. Apply your standards. Clean the data. Validate the results with the people who actually work on those assets. If your "cleaned" data doesn't make sense to a maintenance planner, it's not clean enough.
Step 4: Stage. Load cleaned data into a staging environment. Run validation against MAS schema rules. Fix issues. This is where having a proper staging tool saves enormous time versus doing it in Excel - you can validate thousands of records in minutes instead of days.
Step 5: Scale. Apply the rules you validated in the pilot across all remaining sites and asset categories. This is the bulk of the work and where most projects get bogged down.
Step 6: UAT. Run the upgrade or load in a MAS test environment. Validate that data renders correctly in Manage, Monitor, and Health. Walk the maintenance team through it. Let them poke holes.
Step 7: Go-live. On a reload route, run the final export from staging and import to production MAS. On an upgrade route, upgrade production with the agreed corrections in place. Validate after either.
Steps 1 through 5 are where 80% of the effort goes. The actual technical migration - steps 6 and 7 - is the easy part if the data is clean.
The Timeline Reality
Let's be blunt about timing:
- Maximo 7.6.1 base support: ended on 30 September 2025
- Extended support: check IBM's current terms
- Target: a current MAS 9 release
A realistic data cleanup timeline is 3 to 6 months depending on data volume and quality. The technical migration itself takes weeks. The data preparation takes months.
If you're still on 7.6.1, plan data cleanup alongside the move rather than after it. A rushed migration moves the mess rather than fixing it.
Maximo Migration Questions
How do I migrate from one CMMS to another?
Treat it as a data project with a technical cutover at the end. Inventory the source data, define the target structure and standards, map each field, clean and validate outside production, trial the load in a test environment, then cut over and reconcile. Moving from 7.6 to MAS is a version change within one product, so the data model is largely familiar. Moving from another CMMS into Maximo also means redesigning the hierarchy and mapping every object. See the CMMS data migration guide.
What data should be migrated to a new EAM?
Bring across the master data the system cannot run without: organisations and sites, classifications, locations, assets, items, job plans, PMs, routes and meters. Add open work orders and only as much completed history as you will use. The right period depends on your reporting, warranty and regulatory needs. Archive the rest where it can still be retrieved.
How do you avoid duplicate assets during migration?
Find them before loading. Compare serial number, manufacturer and model, location, classification and normalised description, then have someone who knows the plant confirm each match. Choose one surviving record, map the others to it in a crosswalk, and move their work history and meter readings before retiring them. On reloads, match on stable keys and update existing records rather than adding new ones.
Your Next Steps
-
Get your data out and look at it. Export your asset, location, and classification data. Profile it. How many nulls? How many duplicates? How many broken parent references? You need to know the scale before you can plan.
-
Download our free Maximo to MAS 9 Migration Checklist - it's a 100+ point checklist covering data export sequencing, field mapping, validation rules, and common gotchas. It'll save you from learning the hard lessons the hard way.
-
Decide your classification standard now, not later. This is the decision that takes the longest to get consensus on and affects everything downstream.
-
Start with your highest-criticality assets. You don't need to clean everything at once. Clean the assets that matter most first, migrate those, prove the process, then scale.
-
Consider your tooling. If you're managing this in Excel with 50-tab spreadsheets being emailed between team members, you already know that doesn't scale. Tools that provide hierarchy visualisation, real-time validation, and audit trails exist specifically for this problem.
The organisations that succeed with MAS 9 migration aren't the ones with the biggest budgets or the best infrastructure teams. They're the ones that took their data seriously before the migration started.
Don't move the mess.
This article comes from the team at AssetStage, where we've helped maintenance teams across manufacturing, utilities, and maritime prepare their CMMS data for migration. If you're staring at years of legacy data and wondering where to start, get in touch - or start with our free resources.